Principles
| Architect | L. A. Kersh, Architecture, Inc. |
| General Contractor | John Hyland Const., Inc. |
| Project Manager | George Bleekman, University of Oregon |
Rough timeline
| 1/99 | First discussions with the architect, Lee Kersh, regarding possible sites for the facility. |
| 6/25/01 | Construction began. |
| 2/12/02 | Magnet delivered. |
| 2/28/02 | Scheduled building completion. |
| 4/1/02 | Scheduled MRI system installation and testing completion. |
| 3/5/02 |
First human images. |
Design drawings
Rendering by L. A. Kersh, 2000. |
Previous design phase rendering. |
1% for art ideas. |
Floor plan. |
Courtyard planting plan. |
|
Site photos from Straub Hall stairwell
6/8/01 |
7/9/01 |
7/19/01 |
7/24/01 |
7/31/01 |
8/2/01 |
8/10/01 |
8/17/01 |
8/24/01 |
8/28/01 |
8/29/01 |
8/31/01 |